GMC Commissioning's expertise in complex and integrated central plant systems as well as an acute focus on mission-critical, business continuity provided the owner with the assurance of maintaining operations during the complex testing process.  GMC Cx drove collaboration with the team by pulling together facilities operations, controls and contractors to ensure a joint effort.

Project Overview

This project includes a renovation of the first and second floor in building 1 to support a new 200L cGMP manufacturing lab called Suite D.  The project was turned over in two (2) phases, including commissioning associated with systems serving the turnover spaces. Also included was a retrofit of 600 ton water-cooled chiller plant serving live manufacturing space.  Project included replacement of (3) chillers, (3) cooling towers, conversion  chilled water pumps to variable primary and implementation of Siemens Demand Flow control for Central Plant Optimization. GMC Cx provided design phase and construction phase commissioning.



Systems Commissioned

  • Mechanical

    • (4) 1000 Ton Water-cooled Chillers

    • (1) 1000 Ton Backup Absorption Chiller

    • (12) Open Circuit Cooling Towers

    • Primary, Secondary, and Tertiary Pumps

  • Building Automation System

  • Electrical

  • Plumbing

  • Plant & Process Utilites

  • Process Equipment and Automation